BILL 15
An Act to Amend the Electricity Act
His Majesty, by and with the advice and consent of the Legislative Assembly of New Brunswick, enacts as follows:
1 Section 91 of the Electricity Act, chapter 7 of the Acts of New Brunswick, 2013, is amended
(a)  by adding before subsection (1) the following:
91( 0.1) The following definitions apply in this section.
“data centre” means a data centre as defined in the regulations. (centre de données)
“other business” means other business as defined in the regulations. (autre entreprise)
(b)  by adding after subsection (4) the following:
91( 5) A distribution electric utility shall not negotiate a contract to extend its supply of electricity to a data centre or other business or conduct studies for the purpose of such a negotiation without the prior written approval of the person prescribed by regulation under this subsection.
91( 6) A distribution electric utility shall not extend its supply of electricity to a data centre or other business unless
(a)  the supply of electricity is provided under a contract between the distribution electric utility and the data centre or other business entered into after the commencement of this subsection, and
(b)  the contract was approved in writing by the person prescribed by regulation under this subsection after the commencement of this subsection, subject to any conditions for the approval prescribed by regulation.
91( 7) For greater certainty, subsections (5) and (6) apply to a distribution electric utility that on or before the commencement of this subsection has negotiated a contract to extend its supply of electricity to a data centre or other business or conducted studies for the purpose of negotiating such a contract.
91( 8) For greater certainty, subsections (5) and (6) do not apply to a data centre or other business that had entered into a contract for the supply of electricity by a distribution electric utility on or before the commencement of this subsection.
91( 9) The contract referred to in subsection (6) does not bind the parties to the contract unless the contract is first approved by the person prescribed by regulation under that subsection.
91( 10) The person prescribed by regulation under subsection (6) may only approve a contract referred to in that subsection if that person reasonably expects that the following requirements are met:
(a)  the minimum monetary benefit prescribed by regulation will be realized by the distribution electric utility;
(b)  the supply of electricity to the data centre or other business will not result in increased costs to existing consumers of the distribution electric utility; and
(c)  any other requirement prescribed by regulation.
91( 11) Any amendment to a contract referred to in subsection (6) shall be approved by the person prescribed by regulation under that subsection, subject to any conditions for the approval prescribed by regulation.
91( 12) A contract referred to in subsection (6) that is approved by the person prescribed by regulation under that subsection shall be deemed to be prudent, and the costs and expenses incurred or to be incurred and revenues received or to be received by the distribution electric utility in respect of the contract shall be deemed to be prudent and necessary to enter into and carry out the contract.
91( 13) A consumer of a distribution electric utility under a contract for the supply of electricity approved under subsection (6) or an amendment to the contract approved under subsection (11), as the case may be, shall not be included in any rate class for the purpose of cost allocation and rate design.
91( 14) Section 104 does not apply to the supply of electricity under a contract approved under subsection (6) or an amendment to the contract approved under subsection (11).
91( 15) A data centre or other business that was receiving electricity service immediately before the commencement of this subsection may continue to operate in accordance with the contracts or other arrangements entered into before the commencement of this subsection.
91( 16) The direct and attributable costs prescribed by regulation for the supply of electricity to a data centre or other business shall be borne by the data centre or other business.
91( 17) The accounting treatment for the costs referred to in subsection (16) and the revenues of the distribution electric utility may be prescribed by regulation.
91( 18) Despite anything else in this section, subsections (5) to (17) apply to the following:
(a)  an expansion of a data centre or other business or an increase in required capacity or electric service requirements of a data centre or other business; and
(b)  a conversion of an existing consumer to a data centre or other business, other than a cryptocurrency mining business that has executed a new Network Operating Agreement with the distribution electric utility and whose electric service requirements as of the commencement of this subsection remain unchanged.
2 Subsection 142(1) of the Act is amended
(a)  by adding the following after paragraph (f):
(f.01)  prescribing a person for the purposes of subsection 91(5);
(f.02)  for the purposes of subsection 91(6), prescribing a person to approve a contract between the distribution electric utility and the data centre or other business and prescribing conditions to be met by the data centre or other business for the approval;
(f.03)  prescribing the minimum monetary benefit for the purposes of paragraph 91(10)(a);
(f.04)  prescribing any other requirement for the purposes of paragraph 91(10)(c);
(f.05)  for the purposes of subsection 91(11), prescribing conditions to be met by a data centre or other business for the approval for an amendment to the contract between the distribution electric utility and a data centre or other business;
(f.06)  prescribing direct and attributable costs for the purposes of subsection 91(16);
(f.07)  prescribing the accounting treatment of direct and attributable costs for the purposes of subsection 91(17);
(b)  in paragraph (s) by striking out ““distributed generation”, “large load”, “net metering” and “qualifying costs”” and substituting ““data centre”, “distributed generation”, “large load”, “net metering”, “other business” and “qualifying costs””.